Little Elm HS: Educational Steel Detailing Case Study

Little Elm HS Additions and Renovation: Educational Steel Detailing Case Study

Project Overview

Sloped framing and raker beams, held true across Areas A–F


Little Elm High School’s additions and renovation in Texas is an educational building spanning multiple areas (A–F), each with three levels, and every floor is sloped. Moldtek delivered educational steel detailing for 1,700 tons of main and miscellaneous steel, working through sloped framing on every floor, raker beams in Areas A and B, and roof joists across most of the building, all in close coordination with the joist supplier. What made it demanding was the geometry — slope-driven framing and raker-beam connections — resolved through proactive RFIs on a fast-track, 21-week schedule.

Download the case study
Little Elm High School additions and renovation building exterior
0t
Steel tonnage
0
Levels per area
A–F
Building areas
0
Weeks, fast-track
The Challenge

Sloped framing, raker beams and joist coordination, fast


The complication at Little Elm wasn’t tonnage; 1,700 tons is modest for a school. It was geometry. Sloped framing runs through every floor. Areas A and B carry raker beams and roof joists, plus a pop-up roof in Area A had to be coordinated with the joist supplier, all on a fast-track schedule for a building that had to open on time.

Sloped framing geometry

Extensive sloped framing throughout the project added significant complexity to the detailing and coordination.

Raker-beam conditions

Areas A and B included raker beams that needed special attention for accurate modeling and detailing.

Joist supplier coordination

The roof joists and the Area A pop-up roof required close coordination with the joist supplier to confirm fit-up and deliverability.

Trade coordination at sloped connections

Connections at the sloped beams with rakers had to be coordinated with the other trades to avoid conflicts and stay constructible.

Proactive RFI management

The team initiated RFIs early to resolve coordination concerns inside the schedule.

Little Elm HS steel model with raker-beam and roof-joist coordination callouts across Areas A–F
Moldtek’s Approach

Model the geometry carefully, coordinate the joists early, RFI proactively


  • Sloped and raker geometry modeled carefully

    The team modeled the sloped framing and the raker-beam conditions with particular care given how a school schedule can’t absorb late surprises.

  • Joists coordinated with the supplier

    Roof joists and the Area A pop-up roof were coordinated with the joist supplier to lock reactions, bearing conditions, and spacing.

  • RFIs raised proactively

    Sloped-connection and trade conflicts were cleared before they reached the field.

  • Release-ready output, on schedule

    Release-ready drawings, GA sets, and model deliverables provided on schedule.

Execution Timeline

21 weeks, complex framing without moving the schedule


Proactive RFI tracking through the coordination and QA/QC phases is what kept the sloped-framing and raker-beam issues resolving inside the schedule rather than surfacing on site.

Week 0Week 21
Kickoff
Project alignment
Scope review and planning.
Inputs
Inputs and setup
Standards reviewed and the model set up.
Modelling
3D modeling
Structural steel modeling and preliminary detailing.
Coordination
Trade coordination
Joist integration and clash checks.
QA/QC
QA/QC and RFIs
Quality checks, RFI tracking, and issue resolution.
Release
Release-ready output
Release-ready drawings, GA sets, and model deliverables.
Tools & Standards

Complex framing handled without moving the schedule


The addition was detailed on Moldtek’s standard toolchain and delivered against US structural codes, with all steel fireproofed except the first floor (shop primer).

Detailing toolchain

Tekla Structures SDS/2 AutoCAD Advance Steel Navisworks

Codes & standards

AISC AWS D1.1 OSHA ISO 9001:2015
The Outcome

Complex framing handled without moving the schedule


Early coordination, supplier alignment, and disciplined RFIs translated a geometry-heavy school package into release-ready steel.

Completed Little Elm High School addition exterior
1,700t

Proactive coordination

Minimized clashes and rework through early coordination and RFI management.

A–F

Complex framing handled

Sloped framing, raker beams, and site-specific challenges addressed without impacting the schedule.

21 wks

On-time, quality delivery

Release-ready deliverables provided on schedule with accurate joist-supplier alignment.

At a Glance

Project specifications


LocationTexas, USA
Building typeEducational — high school additions and renovation
Steel tonnage1,700 tons
StructureMultiple areas (A–F), 3 levels each; sloped framing on every floor
Defining conditionsSloped framing throughout; raker beams (Areas A & B); roof joists (Areas A, B, D, E, F) + Area A pop-up roof
Schedule21 weeks (fast-track), kickoff to release-ready
FinishAll steel fireproofed except the first floor (shop primer)
ScopeMain steel + miscellaneous steel (stairs, railings, canopies, embed plates, supports), roof joists, sloped framing, raker-beam connections
Why it worked

“Every floor slopes, Areas A and B carry raker beams, and the roof rides on joists coordinated with a supplier — detailed accurately and cleared through RFIs so the building opens on time.”

Moldtek Detailing Team

Educational Steel Detailing · Little Elm HS Additions and Renovation

Explore our steel detailing services →
Have a project like this?

Let’s detail your next school or institutional building

Planning a school or institutional building — sloped framing, raker beams, a joist-heavy roof, a fixed opening date? That’s the work our structural steel detailing services team does every day.