Location: Kingsport, TN
Type: Industrial
Tonnage: 25
Schedule:Â 4 Weeks
Grand Stair having Rolled Stringers, Rolled Flat bar railing, decorative railing, Landing Supports as Hangers and Vertical bracings.
Challenges are Modeling the Stair Structure with rolled members and rolled railing & Its detailing.
Location: Dallas, TXÂ
Type: Gallery Store And Restaurant
Tonnage: 80
Schedule:Â 8 Weeks
The RH Dallas is a Gallery store building which has 3 levels. Scope included all Misc steel detailing & delegated design.
Among the 3 stairs in scope, it contained Spiral Grand Stairs, Egress Stair towers with railings, Rails at Main Building, Parking Garage and Rug Flipper Support. We have completed the detailing of project in 8 weeks including fabrication release.
It was very challenging to design and detail the Rolled Stairs with radial pans and rolled railings. There is lot of coordination done between Main steel to fix the stairs. During, fabrication stage all stairs are adjusted as per field dimensions.
Location: Denver, CO
Type: Residential
Tonnage: 200
Schedule:Â 24 Weeks
This project is having a scope of Stairs, Stringer rails & other Misc. steel
Location:Â Granite City, IL
Type: Industrial
Tonnage: 100
Schedule:Â 4 Weeks
Waste Gas Stack chimney is a part of Oxygen furnace plant & it is havingÂ
160′-0″ length with Platforms, Ladders and Gratings. Below are major items included in our scope
Circular shape and conical shape stack assemblies.
Platform framing, Ladders, Handrails and Gratings.
Stack splice, platform framing and ladders connection and boltsÂ
Detailing of stack assemblies especially conical shape plate stack assemblies
& Weld preparations at circular stack splices are the most Challenges in this job.
Location: Elk Grove Village, ILÂ Â
Type: Medical Center
Tonnage: 360
Schedule: 12 Weeks  Â
This is extension of existing building. Three floors added above existing roof & stair also extended accordingly. The building is Medical Center.
Since this is expansion of existing building, main challenge is to co-ordinate with field dimensions of existing steel where new steel is being connected. Several RFI raised for existing co-ordination & getting responses.
Building is having façade system at exterior, hence façade co-ordination done like steel framing & roof anchor support steel.
Location:Â Northglenn, COÂ
Type: Civic CenterÂ
Tonnage: 485
Schedule: 15 Weeks
The Northglenn Civic Center project is a Civic Center located at 1, Memorial PKWY in Northglenn, Colorado. This building has 3 Levels (1st, 2nd & Roof) Mainly divided in 3 Areas i.e. Pool, Gymnasium & Theatre. Â
Scope included all Main & Misc. steel detailing & Delegated Design. Main steel includes AB’s, Embeds, Columns, Beams, Vertical Braces, Parapet steel, RTU frames, Screen wall framing, Mock up Framing etc. Misc. steel includes 4 Stair with Rails, Guardrails, Ladders, Dumpster Gates etc. There are Total 4 Sequences for this project.Â
Location: Hartsville, SC
Type: IndustrialÂ
Tonnage: 500
Schedule:Â 10 Weeks
Sonoco Stock Preparation Building is a packaging material manufacturing plant which has 3 levels (Ground floor, Operating and Equipment platform level.) The equipment platform level will be accessible from the operating floor level.
Scope included all main steel, Crane girder rails and exterior metal wall panel support girts detailing.
Equipment support platforms and paper Pulper junk tower tank supporting steel are in scope of work, which we need to detail a radial deck closure and grating support platforms. Coordinating steel guardrail connections around the equipment platforms and stair steel connections with main steel.
There were total 20 sequences to detail in this project & we completed the modeling and detailing work of project within 10 weeks that including fabrication release without fail as we promised with error free.
It was unique experience to co-ordinate with equipment drawings and other trade drawings to detail equipment support platforms and crane rail support connections and mono rails.
Location: Zionsville, IN
Type: EducationalÂ
Tonnage: 550
Schedule:Â 12 Weeks
Zionsville is a elementary school which has total 5Â
Areas A,B,C,D & E
Scope includes base plates, anchor bolts, embeds ,templates,Â
Beams, columns, braces, Sky light opening steel and louversÂ
different types of openingsÂ
There were total 13 sequences to detail in this project & weÂ
completed the detailing of project in 12 weeks including fabrication release.
It is very challenging to form the geometry of the beams and columns and apply connection for the hip and Valley beams.
Location:Â Balmorhea, Texas
Type: School
Tonnage: 739
Schedule: 18 Weeks
The Balmorhea new campus project is a unique structure due to the radial geometry of the project located in the Balmorhea in Texas. The major items included in the scope are Columns, base plates, anchor bolts , Steel moment frame columns, Roof framing, Roof opening frames, bent plates, Expansion joints, Baffle bent plates, Drag struts, Fabric shade connections, Clerestory over two areas.
There were total 21 sequences to detail in this project & we completed the detailing of project for approval and released 70% of steel for fabrication .
It was very challenging to detail on the radial as per the provided radius with intermediate supporting members. All members are in skew and the geometry to match the requirements is a challenging activity. Each area is unique .
Location:Â Biggio drive, Auburn
Type: Commercial Â
Tonnage: 840
Schedule: Â 12 Weeks
One of the complicated Football center. With Tight Schedule.
Having almost 12 Sequences With 3 areas.
Overall Building size is 493’-0 x 217’-0
It is full of Truss members and critical Connections .
Outside of building, is covered with Frames.
Having lot of Misc. items as Stairs , ladders, Rails (Patio rails, Loading dock rails, Aisle rails, Ramps), Counter Brackets, Rails at Concrete stair area.
Schedule of this project is very aggressive and 15 members are Working.