ICCU Plaza: Commercial Steel Detailing Case Study

ICCU Plaza: Commercial Steel Detailing Case Study

Project Overview

A BRB lateral system and a ramp that never stops climbing


ICCU Plaza in Boise, Idaho is a commercial building where Moldtek delivered commercial steel detailing for a 2,323-ton package of main steel framing, gravity- and BRB-column base plates and anchor bolts, mechanical well and roof framing, screen walls, an elevator pit grate, and a deep miscellaneous-steel scope including four stair towers. Two things defined the job: a buckling-restrained brace (BRB) lateral system that demanded early coordination with the BRB supplier and its connection designer, and a continuous parking ramp climbing from Level 1 to Level 6 that had to hold a consistent slope and clearances, all on a fast-track 16-week schedule.

Download the case study
Tekla model of the ICCU Plaza steel frame with its continuous Level 1–6 parking ramp, Boise, Idaho
0t
Steel tonnage
L1–L6
Continuous parking ramp
0
Stair towers
0
Weeks, fast-track
The Challenge

BRB coordination and a continuous ramp, on a fast-track clock


The complication at ICCU Plaza wasn’t raw tonnage. It was two speciality problems running at once: a buckling-restrained brace system that couldn’t be detailed in isolation, and a parking ramp that climbs continuously from Level 1 to Level 6, plus a wide mix of framing types, all inside 16 weeks.

Continuous ramp geometry, L1–L6

The ramp had to hold consistent slope, clearances, and structural performance across every level.

Coordination with the BRB connection designer

Connection interfaces, member sizes, and tolerances all had to align for the BRBs to integrate cleanly.

Early alignment with the BRB supplier

Sharing models and drawings early was essential to confirm requirements and avoid late-stage rework.

Multiple framing types

Miscellaneous steel and roof framing brought diverse member types and connections into a single coordinated model.

Base plate and anchor bolt detailing

Correct dimensions, bolt layouts, and embedment were critical for both fabrication and the concrete interface.

ICCU Plaza steel model with ramp framing, BRB connection and support steel detail callouts
Moldtek’s Approach

Coordinate the BRBs and the ramp first


  • BRB supplier and designer engaged early

    Moldtek aligned with the BRB connection designer and the BRB supplier from the start, sharing models and drawings to lock connection interfaces, member sizes and tolerances.

  • Ramp modeled for consistent slope

    The continuous ramp was modeled for consistent slope and clearance before the surrounding steel closed in around it.

  • Minimized clashes and RFIs

    Resolving the BRB and ramp conditions up front reduced rework and held the detailing package on schedule.

  • Shop-ready release

    Drawings, models, and reports issued for fabrication and erection.

Execution Timeline

16 weeks, speciality interfaces resolved early


Milestone-based releases, with QA/QC at every milestone, are what let shop-ready drawings and models go out on schedule rather than bunching against the deadline.

Week 0Week 16
Wk 0
Kickoff
Project scope reviewed.
Wk 1–2
Inputs
Detailing packages planned.
Wk 3–6
Modelling
Steel and its interfaces modeled, Level 01 to Level 06.
Wk 7–10
Coordination
BRB and ramp conditions coordinated with supplier, designer, architectural, MEP and concrete models.
Wk 11–13
QA/QC and revisions
Milestone-based reviews concentrated on the speciality interfaces.
Wk 14–16
Release-ready output
Shop-ready drawings, models and reports issued.
Tools & Standards

Shop-ready output for a BRB-and-ramp commercial package


The plaza was detailed on Moldtek’s standard toolchain and delivered against US structural codes, so the BRB system and the ramp released constructible and clash-free.

Detailing toolchain

Tekla Structures SDS/2 AutoCAD Advance Steel Navisworks

Codes & standards

AISC AWS D1.1 OSHA ISO 9001:2015
The Outcome

Shop-ready steel for fabrication and erection


Structured reviews, issue resolution, and milestone releases translated a 2,323-ton commercial scope into shop-ready steel.

Completed ICCU Plaza building, Boise, Idaho
2,323t

Commercial scope, cleanly detailed

A clear detailing scope for a 2,323-ton package.

BRB

Strong specialty coordination

Strong BRB and continuous-ramp coordination with the supplier and connection designer.

16 wks

Accurate, on schedule

Accurate, shop-ready deliverables supporting efficient fabrication and erection.

At a Glance

Project specifications


LocationBoise, Idaho, USA
Building typeCommercial plaza
Steel tonnage2,323 tons
Defining featuresBRB (buckling-restrained brace) lateral system; continuous parking ramp, Level 1–6
Schedule16 weeks (fast-track), kickoff to release-ready
Key coordinationBRB supplier + BRB connection designer; architectural, MEP, concrete models
ScopeMain steel, gravity & BRB base plates/anchor bolts, mechanical well & roof framing, screen walls, elevator pit grate, misc. steel (stair towers 01–04, safety posts, handrails, cable & clamps)
Why it worked

“A buckling-restrained brace system coordinated with a specialty supplier and connection designer, and a parking ramp that never stops climbing from Level 1 to Level 6 — detailed clash-free in 16 weeks.”

Moldtek Detailing Team

Commercial Steel Detailing · ICCU Plaza

Explore our steel detailing services →
Have a project like this?

Let’s detail your next BRB or ramp-driven structure

Have a commercial building with a BRB or specialty lateral system, a continuous ramp, or a tight fast-track schedule? That’s the work our structural steel detailing services team does every day.