Sonoco Stock Preparation Building is a packaging material manufacturing plant which has 3 levels (Ground floor, Operating and Equipment platform level.) The equipment platform level will be accessible from the operating floor level.
Tonnage
Schedule
Sonoco Stock Preparation Building is a packaging material manufacturing plant which has 3 levels (Ground floor, Operating and Equipment platform level.) The equipment platform level will be accessible from the operating floor level.
Scope included all main steel, Crane girder rails and exterior metal wall panel support girts detailing.
Equipment support platforms and paper Pulper junk tower tank supporting steel are in scope of work, which we need to detail a radial deck closure and grating support platforms. Coordinating steel guardrail connections around the equipment platforms and stair steel connections with main steel.
There were total 20 sequences to detail in this project & we completed the modeling and detailing work of project within 10 weeks that including fabrication release without fail as we promised with error free.
It was unique experience to co-ordinate with equipment drawings and other trade drawings to detail equipment support platforms and crane rail support connections and mono rails.