MOLSON Coors

Golden, Colorado

Molson Coors is a beverage company having few building in the name of process areas with interior and exterior pipe-racks, stair towers along the side of the building perimeter to get access to top of beverage tanks.

3025

Tonnage

18 Weeks

Schedule

Steel detailing
MOLSON Coors

Molson Coors is a beverage company having few building in the name of process areas with interior and exterior pipe-racks, stair towers along the side of the building perimeter to get access to top of beverage tanks.

This project will replace fermenting, aging, filtering and storage facilities at company’s giant Golden brewery.

It is the second-largest beer-making facility in the world.

Embeds were all over the job as the core structure columns/slabs was designed with concrete. Embed coordination with the steel is major part.

There  were total  55  Sequences to detail in this project.