Zionsville is a elementary school which has total 5
Areas A,B,C,D & E
Tonnage
Schedule
Zionsville is a elementary school which has total 5
Areas A,B,C,D & E
Scope includes base plates, anchor bolts, embeds ,templates,
Beams, columns, braces, Sky light opening steel and louvers
different types of openings
There were total 13 sequences to detail in this project & we
completed the detailing of project in 12 weeks including fabrication release.
It is very challenging to form the geometry of the beams and columns and apply connection for the hip and Valley beams.