LSP New Elementary School

Littleton, CO

This project consists of 5 Areas and steel is available in second level and roof. Roof is two way sloped. Area B is having skew, radial & complex members

This job is having multiple radial grids along with straight grids.

450

Tonnage

10 Weeks

Schedule

Educational
LSP New Elementary School

This project consists of 5 Areas and steel is available in second level and roof. Roof is two way sloped. Area B is having skew, radial & complex members

This job is having multiple radial grids along with straight grids.

Scope of this job is Main Steel, Secondary steel & Misc. Steel

Secondary steel is included with RTU frames, Pour stop angles, Roof deck edge angles, Brick support angles, Window supports, Loose Lintels, Overhead door frames etc.

Misc. steel is included with Stairs, Ramp rails, Swing supports, Backstop supports, Divider curtain supports, Stage partition supports, Guard rails with wire mesh, Wall rails, Ladders, Gates and Bollards etc.  There are 5 sequences in this job.

There are many Joist in this job and Joist Co-ordination is also one of the crucial task.