Parker Water & Sanitation District Headquarters

Parker, CO

All mainsteel columns, beams, bracings AB’s, Deck supports, Hoist beams, Elevator divider beams are in the scope.

Most of the beams are skewed and Misc steel Input not available In drawings. There are considerable RFI’s in this project & EOR is updating the Arch.

150

Tonnage

2 Weeks

Schedule

Parker Water ,Sanitation District Headquarters
Parker Water & Sanitation District Headquarters

All mainsteel columns, beams, bracings AB’s, Deck supports, Hoist beams, Elevator divider beams are in the scope.

Most of the beams are skewed and Misc steel Input not available In drawings. There are considerable RFI’s in this project & EOR is updating the Arch.