Great Lake project is the one of the biggest Cheese production plant in New York.
Tonnage
Schedule
Great Lake project is the one of the biggest Cheese production plant in New York.
This building size is about 1372′ x 644′ with 2470 tons of steel.
It has 10 Areas in it, with 43 steel Sequences . with a full basement totalling around 1 million square foot. Office Area- 9 Floors.
Evaporator, Permeate Dryer, Wpc 80 Dryer & Powder Handling (Towers), Pre-treatment, Cheese Make Unit, Utility & Amenity Area, Conversion Plant, Office Area And Tower Areas.
It is an aggressive schedule Detailing project and Almost 20 members are currently working on this job.
It is having Clean girt with Different Shape, around the towers. Structure is having complicated connections and lot of coordination with other trades.